Industry News

Delayed Infrastructure Projects in India

Delayed Infrastructure Projects in India

Out of 1,681 infrastructure projects, 408 had cost overruns and 814 were delayed, according to the Ministry of Statistics and Programme Implementation, which monitors projects with an investment of 150 crore or more. In May 2023, 408 infrastructure projects had cost overruns of more than 4.80 lakh crore, and 384 infrastructure projects had cost overruns of USD568393.20 million (Rs. 4.66 lakh crore) in the March quarter.

The Ministry's most recent report for May 2023 stated that the total cost overruns of USD58556.10 million (Rs 4,80,074.87 crore) (19.8 6% of the original cost) reflect overall cost overruns of USD294792.60 million (Rs 24,16,872.28 crore), and their anticipated completion cost is likely to be USD353348.70 million (Rs 28,96,947.15 crore). Up until May 2023, these projects cost USD185881.30 million (Rs. 15,23,957.33) crore, or 52.61 percent of what was expected to be spent on them.

However, it stated that if delay was determined based on the most recent completion schedule, the number of delayed projects would decrease to 607. In addition, it stated that neither the tentative gestation period nor the year of commissioning have been reported for 419 projects. Out of the 814 projects that have been delayed, 200 have been delayed for a total of one to twelve months, 183 have been delayed for thirteen to twenty-four months, 300 have been delayed for 25 to sixty months, and 131 have been delayed for more than sixty months. These 814 delayed projects have an average overrun of 37.04 months.

According to various agencies responsible for implementing the project, delays in land acquisition, the acquisition of environmental and forest clearances, and a lack of infrastructure support and links are the causes of time extensions. Other factors included problems with law and order, a change in scope, tendering, equipment supply, and finalization of detailed engineering, as well as delays in tie-up for project financing. The report also mentioned the state-wide COVID-19 lockdowns that were imposed in 2020 and 2021 as a reason for the delay in putting these projects into action. For many projects, it has also been noticed that project executing agencies are not reporting revised cost estimates and commissioning schedules, which suggests that time/cost overrun figures are not being reported properly.

Relevant News